Thermochem (TCI) performed the well test chemistry and initial silica scale inhibition testing at Silangkitang (SIL) for Unocal, 1995.
TCI supplied the mufflers (LECM) and PTS tools, and performed all the well testing services at the Sarulla project (32 wells) for SOL, 2014 – present.
TCI built and operated a Pilot Test Unit to evaluate NCG injection for pH-modification at SIL and Namora-I-Langit (NIL) plants, 2015 – present.
TCI redesigned and provided new equipment to retrofit the pH-modification systems at SIL and NIL plants, after problems caused by EPC contractor design discovered on commissioning, 2016 – present.
TCI designed and supplied multi-nozzle isokinetic probes and on-line steam analyzers for steam purity measurement at SIL and NIL plants, 2016 – present.
TCI completed an acid-brine downhole corrosion mitigation pilot test, and moved to full commercial operations of same process on 5 production wells – present.